Skip to content

Albertville Valley sand mine asking for 60-day extension on reclamation permit

By LeAnn R. Ralph

TOWN OF HOWARD  —  Representatives for the proposed Albertville Valley sand mine are asking for a 60-day extension on the mine reclamation permit.

Vernon Schindler, chair of the Howard Town Board, announced at the October 6 meeting that Northern Sands/Red Flint Group, which is proposing to operate a sand mine covering about 1,300 acres a few miles southeast of Colfax, have asked Chippewa County Land Conservation and Forest Management for a 60-day extension on the reclamation permit.

Schindler said he had no other details except that company had asked for the extension and that the 60-day extension would change the deadline to November 19.

Seth Ebel of Chippewa County Land Conservation and Forest Management confirmed in an e-mail message to the Colfax Messenger that the company is asking for an extension.

“Northern Sands has requested and the LCFM (Land Conservation and Forest Management) has granted an extension to the permitting timeframe for the Northern Sands nonmetallic mining reclamation permit application,” Ebel wrote.

“The purpose of the extension is to allow Northern Sands to address issues raised in the public hearing regarding the adequacy of the plan in addressing the reclamation standards and requirements contained in Wisconsin Administrative Code NR135 and the Chippewa County nonmetallic mining reclamation ordinance,” he said.

“Any subsequent changes to the permit application made by Northern Sands will be posted on our website at the time a permit decision is made by Chippewa County,” Ebel said.

Chippewa County Land Conservation and Forest Management held a public hearing on the reclamation plan for the Albertville Valley sand mine July 29.

SCS Engineers out of Madison, a company that specializes in environmental consulting and contracting, reviewed the proposed reclamation plan and made a number of recommendations.

One of the recommendations is to do a pre-mining detailed analysis of the groundwater and install a minimum of three water table wells in each area where the frac sand will be mined and to measure the water levels monthly for one year.

SCS also is recommending that piezometers be installed next to the water table wells to evaluate the vertical flow pattern of the groundwater.

The information from the groundwater monitoring should then be used to prepare groundwater flow maps for the months with the highest and lowest groundwater elevations, according to the SCS report.

The detailed analysis with site-specific data is needed to meet the provisions for groundwater management and protection in Wisconsin’s administrative code NR 135.08, the report states.

Experience has shown that in this part of Wisconsin, the water table is not always where it was thought to be.

At the July 29 hearing on the reclamation plan, Ron Koshoshek, the Town of Howard’s mining consultant, said that the groundwater location at the S&S mine in the Town of Howard on county Highway B turned out to be closer to the surface, which means that the number of tons of sand available to be mined was cut in half, from 33 million tons down to 13 to 15 million tons.

Chippewa County regulations allow frac sand mining to within ten feet of the groundwater.

Watersheds

Another complicating factor for the Albertville Valley sand mine is that the proposed location involves two different watersheds, one for Elk Creek, which drains to the Chippewa River, and one for Eighteen Mile Creek, which drains to the Red Cedar River.

The draft reclamation plan indicates that wetlands will be identified prior to the start of mining in each phase and that the wetlands will be avoided during mining.

The draft plan states there will be a setback of 75 feet from wetlands identified by the state Department of Natural Resources, and a setback of 300 feet from steams identified by U.S. Geological Survey maps.

To meet the provisions of surface water and wetland protection in NR135.07, field observations are needed, along with detailed current site-specific information, according to the SCS report.

SCS recommends a field study to identify the location of all wetlands and water bodies, including intermittent streams, and to establish a buffer zone of 100 feet from the wetland boundaries and the center lines of water bodies.

A map should be prepared showing the location of wetlands, water bodies and setbacks, and the map should be submitted to Chippewa County as a revision to the draft reclamation plan, the report says.

The reclamation plan should be reviewed and revised as needed to assure wetland and stream hydrology are preserved by final grading, revegetation, pond discharges and stormwater diversions, the SCS report states.

According to Koshoshek, Northern Sands/Red Flint Group must have all of the permits needed from Chippewa County and the DNR and must collect the information needed before the Howard Town Board will discuss a non-metallic mining license or a developer’s agreement.

Public comments

In other business during the October 6 Howard Town Board meeting, board members decided not take any action on limiting public comments.

At the September town board meeting, Todd Wanish, town board supervisor, said he had heard from township residents that they did not believe Town of Colfax residents, or Dunn County residents in general, should be allowed to make comments at the Howard board meeting.

Several residents in the Town of Colfax live directly across the road from the proposed Albertville Valley sand mine and have, at times, asked questions and made comments to the Howard Town Board about the proposed mine.

If the Howard Town Board sets a time limit on public comments, the board board would have to limit the comments from Howard residents as well, Schindler said.

Wanish said he was not going “to push the issue” because he believes Governor Scott Walker will take rights away for local control.

“I don’t think we should limit (comment) time,” said Dennis Dvoracek, town board supervisor.