GC School Board gives green light to Miron Construction
GLENWOOD CITY — The Glenwood City Board of Education heard from Tim Andrews, Vice President of Northern Operations at Miron Construction on Monday night in regards to the bids for the referendum projects.
The items the Board originally requested to be in the referendum including HVAC/Plumbing upgrades, new and renovated offices and safety features like lights in the parking lot were shown with their official bid prices.
The Board reviewed all the items and their costs and approved the presented budget by Andrews unanimously.
The cost when all is said and done looks to fall within the allotted referendum amount around $9.2 million. With the current approval, the Board has just over $53,000 left in the budget to “play” with if needed.
However, an estimated $120,000 could be needed if the State recommends that a section of the building needs reinforcements.
Inspectors from SW Wold Construction did an evaluation of the roof in a section of the High School and determined it to have “stress points” according to their standards.
They recommended it be reinforced with steel beams, but this was not a necessity unless the State comes in and says so, which means the budget as stands does not have the cost included.
If the State does say yes to the need for added beams, then the Board could be faced with using contingency money to cover the overage cost.
With the Boards approval of the budget, Miron Construction can now move forward with issuing contracts to all hired subcontractors.
The plan will be sent to the State level and once approved with proper permits sent out, construction will be allowed to begin.
Superintendent, Tim Johnson also stated that the Asbestos contract came back nearly $8,000 less due to an overall lack of asbestos in the buildings, which is great news.
The majority of the remaining asbestos to be found appears to be on some of the glue that holds the tiles in place.
Back to the Administrator reports, Assistant Principal, Nicole Brite talked about the upcoming Summer School plan, which has several new and exciting updates.
Students attending sessions from 8:00 a.m. to 12:00 p.m. will now have the option to purchase breakfast and lunch with the cost to be around $2.50 per day.
Sessions offered will be STAR Remediation, Enrichment Classes, and Sports Skills with golf, baseball, softball, basketball and football. Also there will be TOPS, Agriculture and Band available.
Students will also have a transportation option now with a means of travel to and from swimming lessons if necessary.
Also parents are to note that with the upcoming projects at the school, Summer School classes will be held at Holy Cross Lutheran Church as needed.
Other action items included the Board’s approval to dissolve State Trust Fund 73 and they approved to post for the position of Guidance Counselor at 20 percent time for the 2016-17 school year.
The next meeting is scheduling for Monday, February 22 at 6:30 p.m.