Construction work continuing on St. Croix Crossing; WIS 35 detour to begin this week
Less than one year ago, work commenced on the decades-delayed St. Croix Crossing project that will connect St. Croix County (WI) and Washington County (MN) with a modern, 4-lane bridge by mid-2016.
Eight sets of pier foundations constructed in the St. Croix River were deemed substantially complete in late December. Work transitioned to Lunda/Ames Joint Venture, the low bidder for the bridge superstructure. By mid-February, Lunda/Ames constructed a temporary causeway from the Minnesota shore to the first set of river pier foundations.
Despite cold temperatures, a major milestone was achieved on Saturday, March 1, 2014 as St. Croix Crossing crews began the process of lifting the first form onto Pier 8W, near the Minnesota shore. Construction crews will continue installing forms on the piers and pouring concrete, allowing the balance of the piers above the water line to take shape. A webcam allows viewers to observe moment-by-moment progress at http://www.dot.state.mn.us/stcroixcrossing/webcam.html.
Contractors are working on the 23 footings needed for Piers 1-7, all located on-land in Minnesota. In late December, crews started driving steel beams into the ground to establish the foundations. By late February, about 35% of the pile driving had been completed, and the contractors estimate that the more than 10,000 feet of piling is now in the ground. This work will continue through May, 2014.
Beginning Monday, March 17 WIS 35 closed to traffic to allow for the construction of the new WIS 35 overpass over the future WIS 64 that will connect with the new St. Croix Crossing.
The highway will be closed between County Road V and Houlton. Motorists on WIS 35 will use County Road E and County Road V until the state highway re-opens to traffic in July, weather permitting. In order to minimize the inconvenience of a longer-term detour, crews will be working 24-hour shifts. Their work schedule will begin Monday mornings through Saturday mornings for about two months.
This year, crews will grade the new WIS 64 road surface between the river bluff and just north of County Road E. Grading work will continue in 2015 in the north project area to 150th Avenue. The new WIS 64 will be paved in 2016 and open to traffic simultaneously with the new St. Croix Crossing.
H. James & Sons, Inc. based in Fennimore, Wis., is constructing the first portion of the approach work.
Additional Project Info
The overall three-mile project completes the WIS 64 majors project that was built in the early 2000s.
The four lane expressway from New Richmond to Houlton will now tie-in to the new St. Croix Crossing structure over the St. Croix River in 2016. The entire project will include:
• WIS 35 overpass, located near the main bridge
• WIS 35/County E interchange
• Pedestrian and bike path
• Two roundabouts located at the ramp terminals
Connecting with the Project
Stay connected, ask questions or provide comments to the St. Croix Crossing project team by visiting the project website (http://www.dot.state.mn.us/stcroixcrossing/), signing up for weekly email updates, calling the hotline at 1-855-GO-CROIX (462-7649), liking saintcroixcrossingmndot on Facebook, following stcroixcrossings on Twitter, downloading the new 511 mobile app or visit www.511mn.org, and/or stopping by the project office at 1862 Greeley St. S., Stillwater. Hours are 8 a.m. to 4:30 p.m. Monday-Friday.