COLFAX — The Colfax Village Board has approved moving forward with projects on Riverview Avenue, High Street and Dunn Street.
Cost estimates are $291,000 for Riverview, $148,000 for 200 feet of High Street and $90,000 for Dunn Street, for a total cost estimate of $530,000, said Lynn Niggemann, village administrator-clerk-treasurer, at the Colfax Village Board’s December 14 meeting.
Problem areas include a storm drain that must be repaired on Riverview, sewer lines that must be replaced on Riverview and on High Street and no sewer lines in the area of new development on the east side of Dunn Street.
The village board will have to prioritize when and how the street projects are completed, and the cost may have to be financed, Niggemann said.
Gareth Shambeau of Ayres Associates attended the meeting to talk about the scope of work.
The village board has signed a “master agreement” with Ayres, so adding the Dunn Street project is a simple one-page addition, Shambeau said.
The village board had originally discussed projects on Riverview, High and Oak Street for 2021.
With the recent plans by Homes by Croix Creek to eventually build five new homes in the East View residential development, Dunn Street has become a priority as well. While the first house will have sewer service, the other houses that Homes by Croix Creek would build along Dunn Street would not have sewer service.
Which project would take priority in the spring? asked Mark Halpin, village trustee.
Dunn Street has building projects, but Riverview and High Street have sewer problems, Niggemann said.
The holes in the sewer lines on Riverview and High Street have gotten worse, said Rand Bates, director of public works.
“The holes are a major problem,” he said.
The best way to manage the project would be to solicit bids for all three from one contractor and then decide how to prioritize and how to finance, said Scott Gunnufson, village president.
There will be cost savings if one contractor bids on all three projects, Shambeau said.
Gary Stene, village trustee, suggested contacting Sean Lentz of Ehlers Inc. so Lentz can advise the village on financing options for the street projects.
Dunn Street is in a Tax Increment District, Niggemann noted.
If two houses are valued at a total of $400,000, what is the increase in property taxes the village will receive? Stene asked.
Houses valued at $400,000 would add between $10,000 and $11,000 in property taxes, Niggemann said.
Different parts of the street projects can be bid as “alternates,” and when the village board considers the bids, the board can decide then on the priority, Shambeau said.
The Colfax Village Board approved a motion authorizing Shambeau to add Dunn Street to the scope of work and to send the projects out for bids.
Shambeau said he would provide an addendum to the village board that includes Dunn Street so that the village board can consider the addendum at the next meeting.
Riverview
A camera must be used to view the storm sewer on Riverview to find out where it changes from steel to cement and to see the condition of the pipe, Bates said.
The storm sewer goes through Lila Whitted’s yard, and the bank has been eroding since 2011, he said.
Enough of the bank has eroded away that the pipe is hanging out in the air when it used to be underground, Stene said.
As per state Department of Natural Resources regulations, the village can replace the storm sewer “in kind” but if the storm sewer is changed, then the village would need a waterway permit, Shambeau said.
The water never gets to where the pipe is, Stene said.
If fill had to hauled in for the storm sewer, for example, even though the storm sewer pipe is above the water, the fill would be below the water mark, and then you are working in the waterway, Niggemann said.
One solution would be to put the pipe back where it is and install rip-rap to the water’s edge, Shambeau said.
Curb and gutter installed on Riverview will cut down on the water coming from the road, so the only water going through the storm sewer pipe will be from the yard. The pipe can be fixed, and the amount of water going into the river can be controlled, he said.
All of the water from the road is now going into the storm sewer. In 2011, there was an unsafe sample of drinking water, and the hydrant was flushed, which started the erosion on the river bank by the storm sewer on Riverview, and now every heavy rain makes it worse, Bates said.
WE Energies
In a matter related to the East View residential development, the Colfax Village Board approved a public works utility permit for WE Energies for 304 Dunn Street.
According to the village’s ordinances, utilities cannot be installed from November 15 until April 1, except if approved by the village board for an emergency, Niggemann said.
The new house currently being built in East View will need natural gas service when the house is enclosed in order for construction to continue this winter, she said.
Niggemann said she had called an engineer about the utility installation and had been told smaller municipalities often have a “frozen ground” ordinance because patching of the road is a concern during the winter.
WE Energies will be boring under Dunn Street and will trench the service to the house. The work will be completed in January, she said.
WE Energies will go through the frost on top and then will bore under the street and trench, Bates said.
Sewer and water has already been installed to the lot, he said, in response to a question from Gunnufson.
Stene wondered if the village board should consider amending the ordinance to avoid slowing down any future construction but Gunnufson noted the ordinance allows the village board to consider the installation of utilities on a case by case basis.
The Colfax Village Board unanimously approved a motion for a permit for WE Energies to install utilities at 304 Dunn Street.
Other business
In other business, the Colfax Village Board:
• Approved a facility rental for the Colfax Fire Department to use the Colfax Fairgrounds December 19 from 4 p.m. to 5:30 p.m.for the Colfantastic Christmas event.
• Approved a second-hand jewelry dealer license for Twice Blessed Treasures from January 1, 2021, to December 31, 2021.
• Approved a contract with Weber Inspection for 2021 for Fred Weber to act as the village’s building inspector.
• Approved moving forward with the purchase of new election equipment in 2021. The county asked all municipalities to go together to purchase new election equipment so that all of the municipalities would receive a discount, Gunnufson said. The village budgeted $9,000 in 2020 and 2021 for the new equipment, so the money will be available, Niggemann said. The election equipment currently used by municipalities will eventually no longer be supported for repairs or updates by maintenance companies. The amount quoted for the cost of the equipment represents a savings of $2,000 on the amount that was budgeted, Gunnufson noted.
• Approved paying an invoice for $4,000 from JWR out of Johnson Creek for four used Nedland compactors for Colfax Solid Waste and Recycling. The village will pay part of the equipment cost as a member of the Responsible Unit, and the RU will reimburse the remainder of the cost to the village once the account is set up and there are checks available, Niggemann said. The RU will ask the member municipalities to make deposits for equipment sooner rather than later, and most if not all of the municipalities appear to be prepared to make deposits in January, she said. The extra compactors will be used to compact recyclables for single stream recycling. The Colfax RU, in addition to the Village of Colfax, includes the Towns of Colfax, Grant, Otter Creek, Wilson, Elk Mound, Spring Brook and the Village of Elk Mound.
• Approved service agreements with First Choice Computer Recycling LLC and Liberty Tire Recycling for the Colfax Responsible Unit.