WIS 29 project between County B and I-94 in Dunn County underway

To invest in Wisconsin’s transportation system, Gov. Tony Evers has signed a $3.1 million contract to improve WIS 29, between County B and I-94, in the towns of Red Cedar and Elk Mound in Dunn County. Work began Tuesday, August 24.

Monarch Paving Co. is the prime contractor for the project. Construction will entail milling the existing pavement and overlaying it with asphalt, along with cleaning, clearing, repairing or replacing culverts.

During construction, WIS 29 will be open to traffic with lane closures controlled by flagging operations.

Construction is scheduled for completion in mid-October. The schedule is dependent on favorable weather conditions and construction progress.

For more information regarding traffic impacts, transportation news and improvement project updates in Wisconsin’s Northwest Region follow on Twitter: @WisDOTnorthwest, and visit the region’s 511 website: projects.511wi.gov/region/northwest/

Motorists are reminded that using handheld cell phones in Wisconsin work zones is illegal. Alerts and updates provided via these sites are not intended for use while driving. When driving, your focus should be on driving.