City gets second opinion on lagoon upgrades

GLENWOOD CITY — The City Council entertained a representative from a Rice Lake engineering firm to discuss upgrades to the city’s wastewater treatment facility.

Gary Strand of Cooper Engineering presented the council with an upgrade plan that took a different path than the plan from a DePere, Wisconsin firm that was hired by Cedar Corporation, a plan that the Council reviewed on October 27th.

The first plan had a price tag of nearly a million dollars and the upgrade plan that was presented to the Council Monday, evening, November 9th at a special meeting, had a price tag of three-quarters of a million dollars.

Cooper Engineering is the firm that did the engineering work on the facility when it was first constructed back in the 1960s.

Mayor John Larson related that getting a second opinion is just like getting a second opinion from a different doctor. “I have been upfront with Cedar about looking at a second opinion,” he told the meeting.

Strand told the Council that, “we can enhance the operation of what you have.” He noted that the current treatment plant is very flexible and that the treatment for ammonia and phosphorus is also very flexible.

In Cooper’s plan the main change would be to divide the large artificial wetland into six sections and create a seepage cell which would allow the treated wastewater to seep into the ground. In his plan about thirty percent of the 23 acre wetland would be divided into four seepage cells.

Strand’s information sheet indicated that, “the existing artificial wetland dates back to the 1960s, and has never been maintained. Because of this, an organic layer has built up which restricts the infiltration rate. However, the organic growth has also provided for ammonia reduction uptake.”

Strand told the council, “there is no reason that we cannot get this system working as a seeping cell and the flow will never get to the artificial wetland.”

Mayor Larson noted at present the treated wastewater that comes from the existing aeration ponds is very clean but its quality drops as it flows through the artificial wetland. Strand stated that they knew that, and would bypass that wetland with piping and directed the treated water to the west into the wetland outside of the facility.

Strand also indicated that the city would not have to do testing for ammonia or phosphorus using the seepage cell idea.

Also included in Cooper’s plan would be updating the blower building and piping and cleaning out the existing aeration ponds.

The plan of dividing the wetland includes the construction of “four cells of 66,000 square feet each along with two artificial wetland cells of 263,000 square feet each. Instead of removing the organic layer from the site, it would be relocated to the edges of the remaining artificial wetland to allow it to dry and break down. It could be land applied several years later, if necessary. Depending on the consistency, it may also be used to construct portions of the dividing dikes,” the report stated.

Strand concluded by telling the Council that, “you are very fortunate to have the discharge permit you have.”