Skip to content

Contractor recommends municipal building drainage through Tower Park

By LeAnn R. Ralph

COLFAX  —  Instead of routing the runoff behind the Colfax Municipal Building, a contractor is now recommending that roof runoff be routed through Tower Park to the storm sewer on Main Street.

Tony Eaton of A Breeze Construction LLC spoke to the Colfax Village Board at a special meeting October 5 regarding the change in his recommendation.

Bob Sworski, vice president and senior project manager with CBS Squared, an architectural and engineering company out of Chippewa Falls, also attended the special meeting.

At a public property committee several weeks ago, Sworski spoke about the water infiltration problems in the Colfax Municipal Building basement and the recommendations from A Breeze to improve the drainage from roof runoff to keep water away from the building.

Channeling the roof runoff away from the building is expected to help eliminate standing water in the basement following heavy rain.

Sworski wrote the original report about water infiltration problems in the municipal building basement in the late 1990s when he was employed by another company.

The original proposal from A Breeze was to route the water to catch basins installed in the parking lot in back of the building and then drain the water to the Red Cedar River.

At the September 28 village board meeting, village trustees learned that routing stormwater toward the river may require a stormwater permit from the state Department of Natural Resources.

An easement also would be needed from Bill Berres because of the Berres Family and Sports Chiropractic building just north of the municipal building.

Village officials are hoping to complete the work around the municipal building this fall to improve drainage, but acquiring a DNR permit takes time, and A Breeze will not pour concrete after October 15.

Tower Park

An alternative to draining the water to the parking lot in back, Sworski told the village board at the October 5 meeting, would be to route the stormwater to catch basins in Tower Park and then route the water to the 42-inch storm sewer along Main Street.

Sworski said he believed it would be a shorter process to obtain an agreement from the state Department of Transportation for the storm sewer along Main Street than to obtain a stormwater permit from the DNR.

Eaton reiterated that A Breeze will not warranty concrete after October 15.

“No one warranties concrete after October 15,” he said.

The plan would be to pour concrete all the way around the building to help channel water away from the foundation and then direct the rain water coming off the building and from the downspouts toward catch basins that would be drained to the storm sewer, Eaton explained.

Eaton said he has done more than one hundred projects dealing with drainage.

“If I can’t fix it, I don’t do it,” he said.

Membrane

Eaton said he also is planning to install rubber membrane around the building to keep the water from soaking into the ground, and therefore, to keep it from infiltrating the municipal building basement.

In the interest of full disclosure, Eaton said he wanted to make sure the village board was aware that the rubber membrane he would be installing is not new membrane.

The rubber is actually ten years old and comes from roofs at Chippewa Valley Technical College that were replaced, he said.

The rubber actually has a 60-year non-prorated warranty for an area that has high UV exposure, he said.

The application at the municipal building would be a low UV exposure for the rubber membrane, Eaton noted.

The membrane for the project will cost $1,800, he said.

The original proposal from A Breeze was a little more than $54,000.

The additional catch basins, rubber membrane, pipe and the fee for CBS Squared is expected to bring the cost of the project closer to $67,000.

Trees

Eaton also said he would recommend taking down the trees in Tower Park.

“We can go around the trees with the pipes, but I am recommending taking out the trees,” he said, noting that installing the drainage pipes and catch basins will damage the tree roots to the point where the trees probably would not survive.

Approval

The Colfax Village Board approved a motion to move forward with the project proposed by A Breeze Construction.

Village President Scott Gunnufson and Village Trustees Mark Halpin, Dave Wolff, Annie Schieber and Jeremy Klukas voted in favor of the motion.

Village Trustee Carey Davis voted “no” on the motion.

The village of Colfax has $77,912 in one designated fund for the municipal building basement and $165,280 in another fund designated for village hall improvements.

The $77,912 comes from $50,000 the village board set aside for the municipal building basement in 1999 and from private donations for improving the basement.

Other business

In other business, the Colfax Village Board approved a street use permit for a street closing October 10  on West River Street between Cedar Street and Maple Street requested by Jen Laska for a Halloween party.