Colfax moves forward with Phase 2 in East View
PROTECTED CONTENT
If you’re a current subscriber, log in below. If you would like to subscribe, please click the subscribe tab above.
Username and Password Help
Please enter your email and we will send you a password reset link.
By LeAnn R. Ralph
COLFAX — Seems like it’s been a long time coming, but the Village of Colfax is now ready to move forward with Phase 2 in the East View residential development on Dunn Street.
The Colfax Plan Commission met May 20 and is recommending that the village board move forward with the original concept of three single family lots and two multi-family lots in Phase 2, along with installing sewer and water mains as well as platting and recording the five lots as a major subdivision, said Lynn Niggemann, village administrator-clerk-treasurer, at the Colfax Village Board’s May 24 meeting.
The village could create four lots in five years by certified survey map (CSM) but because there will be five lots created at once, the creation of the lots will require approval of the preliminary plat and the final plat by the state of Wisconsin, she said.
Andrew De Moe of Andy’s Custom Concrete has expressed interest in building a triplex in East View.
The units in the triplex would be sold to individuals who would be considered the homeowners, and the multi-family lot would have to be divided into three lots so that each owner would actually own the lot as well.
The concept for the triplex is similar to a twin home in that it is considered a “zero lot line” development.
The multi-family lots will be platted as two lots, rather than the six required for two triplex units, so there is flexibility in the potential for development, said Jody Albricht, village president.
The multi-family lots can always be divided into three lots later on when the triplex project is moving forward, he said.
Contracting with Cedar Corporation to plat the major subdivision of five lots and obtain approval through the state would cost $6,500, Niggemann said.
Once Cedar Corp. submits the plat and receives preliminary approval from the state, the final approval usually does not take very long if there are no changes, Albricht said.
Cedar Corp. was not able to give a timeline for the approval because some state employees have been working from home because of the pandemic, so the process takes somewhat longer than in the past, Niggemann said.
Sewer and water
Installing sanitary sewer and water mains for East View, along with asphalt for Dunn Street, would cost $244,000, according to an estimate from Ayres Associates.
The water main portion would be $47,000, and the sanitary sewer would be $65,500, while the street construction would be $131,700.
The original estimate for Dunn Street — $87,500 — was for sanitary sewer and street construction from Third Avenue north to the single family lots in Phase 2, since that section of the project already has water main installed, said Rand Bates, director of public works.
The new estimate for sewer and water goes from Fourth Avenue to the end of the property owned by the village, which is across the street from the mobile home court, he said.
The $244,000 includes the original estimate of $87,500, Niggemann said.
Financing
The village board approved borrowing $120,000 for the Dunn Street project in February to make the final expenditure allowed for Tax Increment Finance District 4 by the February 22 deadline, Niggemann said.
No more expenditures can be made out of TID 4, so the village board should consider creating a TID 5 overlay, she said.
Creating TID 5 would require a meeting of the Joint Review Board of representatives for the village, the Colfax school district, Chippewa Valley Technical College and Dunn County, Niggemann said.
At the May 20 plan commission meeting, representatives for Ehlers and Associates attended the meeting by telephone and provided a variety of information about financing.
Did Ehlers talk about a TID 5 overlay? asked Gary Stene, village trustee.
TID 5 could be created by the end of July, Niggemann said.
TID 5 would have to be a mixed use TID in order to include residential, and a mixed use TID can have 35 percent residential and 65 percent commercial and industrial, Albricht said.
Mixed use is the only option, and the planning must include 100 percent of the TID, which would have to extend west to the industrial park to include the commercial and industrial, Niggemann said.
The village does not want to create a situation where there are lots with no sewer and water, Albricht said.
The plan commission is saying to move forward so the village does not end up with lots with no sewer and water, Stene said.
Stene noted that past experience on village board has shown him “taking the cheap route comes back to bite you.”
Sean Lentz and Ehlers as financial consultants “are good to work with. I have confidence in them,” he said.
As long as the village stays within the guidelines for the TID and considers the proposed valuation for the new development and does not borrow more than the valuation, there is no tax liability on the residents, Stene said.
“A TIF is a no-brainer if you don’t spend more than the valuation,” he said.
Increased valuation in the village also will allow the tax levy to increase under the state-imposed revenue limits, Stene said.
ARA
Under the American Recovery Act, Colfax also will be receiving $114,000 in two installments, over a two-year period, Niggemann said.
Water and sewer are allowable expenditures, so that could bring the cost of the water and sewer down in Phase 2, she said, noting the money must be spent by 2026.
The village could also save the American Recovery Act money and use it on repairing sewer and water in the older parts of the village and use the TID money on new construction, Albricht said.
The village could do sewer and water on two streets for $114,000 and could wait a year and do two streets together, which would probably result in a better price on the asphalt, Stene said.
What if it all goes well, and the village has to buy more land? Would another TID be able to cover that?asked Margaret Burcham, village trustee.
The recommendation from Ehlers is to “slow down and get this figured out now” and not to think about buying more land until later, Niggemann said.
Could a rail spur in the industrial park be covered by TID 5? Burcham asked.
Railroads are giving incentives to companies, so an incentive from the village would not be a good use of the funds available, Albricht said.
The last estimate for a rail spur was $1.8 million, Niggemann said.
Bid
The additional work on Dunn Street is too much to be included in a change order and would have to be bid as a second contract, Niggemann said.
The work could cost more because the contractors will be trying to fit it into their schedules, and the project may or may not be finished this year, she said, noting it might be possible to do the underground work this year on the sewer and water mains and then complete the asphalt next year.
What happens if the street is finished and then gets torn up during the residential construction? asked Carey Davis, village trustee.
If the asphalt does not hold up, “someone will fix it,” Bates said, noting that it would not be the village since a new street should hold up under traffic.
The street could be gravel until after the construction in the subdivision is finished, Davis said.
The new asphalt would be designed to hold to up to traffic, De Moe said.
Is the plan commission “okay” if the Dunn Street project is not completed this year? asked Mark Halpin, village trustee.
Completing the project over two years did not come up as an item of discussion at the plan commission, Albricht said.
Niggemann suggested calling Gareth Shambeau, the civil engineer with Ayres who had provided the estimate, to ask if he had an idea of how much more the Dunn Street project could cost if it was advertised for bids.
Much will depend on how busy the contractors are for the season. They will say they can fit it in, but the village will pay a premium price, Shambeau said after Niggemann had put him on speaker phone.
On the other hand, the estimate of $244,000 already includes a 15 percent contingency, so another 5 percent would most likely cover the cost, he said, adding that he would be “comfortable with 5 percent.”
The Colfax Village Board unanimously approved a motion to follow the Colfax Plan Commission’s recommendations to develop Phase 2 of East View with three single family lots and two multi-family lots, to complete the sewer and water mains for Phase 2 and to move forward with platting the five lots as a major subdivision that will require review and approval by the state of Wisconsin at a cost not to exceed $6,500.