Multi-county pavement marking project to be completed in 2021

To invest in Wisconsin’s transportation system, Gov. Tony Evers has signed a $1.04 million contract for pavement marking on highways in 14 of the Norwest Region’s 20 counties. Work is scheduled to begin Monday, May 17, in Trempealeau County.

Sir Lines-A-Lot of Edina, Minn., is the prime contractor for the project. Work will entail longline marking of centerlines and edge lines and special marking of words, arrows, stop bars, diagonals, curbs and crosswalks.

Longline marking is planned in the following counties:

• Ashland: US 2.

• Buffalo: WIS 25, WIS 35, WIS 37, WIS 88 and US 10.

• Douglas: WIS 27.

• Dunn: WIS 40 and WIS 79.

• Eau Claire: WIS 12, WIS 93 and US 12.

• Jackson: WIS 54 and US 12/WIS 27.

• Pepin: WIS 25.

• Pierce: WIS 35 and WIS 128.

• Polk: WIS 35, WIS 48, WIS 65, US 8 and US 63.

• Rusk: WIS 73.

• St. Croix: Carmichael Road, WIS 65, WIS 128 and US 12.

• Taylor: WIS 13.

• Trempealeau: WIS 93, WIS 95, US 10 and US 53.

• Washburn: WIS 70 and US 63.

Special marking is planned in the following counties:

• Dunn: WIS 40, WIS 79 and WIS 85.

• Eau Claire: Various highways.

• St. Croix: WIS 65 and I-94 ramps.

• Taylor: WIS 13, WIS 64 and WIS 102.

Highways will remain open, but work will result in lane closures. Marking on busier segments will be completed at night.

Work is scheduled for completion in October.

For more info: follow on Twitter: @WisDOTnorthwest, and visit the region’s 511 website: projects.511wi.gov/region/northwest/