Colfax adds Dunn Street to scope of services for $9,000
PROTECTED CONTENT
If you’re a current subscriber, log in below. If you would like to subscribe, please click the subscribe tab above.
Username and Password Help
Please enter your email and we will send you a password reset link.
By LeAnn R. Ralph
COLFAX — The Colfax Village Board has approved adding Dunn Street to the scope of services agreement with Ayres Associates that already covers Riverview Avenue and High Street for an additional $9,000.
Dunn Street can be added to the agreement as an amendment in the design and bidding phase and the construction phase to provide an option for street projects, said Gareth Shambeau of Ayres Associates at the Colfax Village Board’s January 25 meeting.
The village board approved the scope of services for Riverview Avenue and High Street at the December 14 meeting.
The topographic survey for Dunn Street has already been completed. Adding Dunn Street to the design and bidding phase increases the cost from $25,300 to $30,600. Adding Dunn Street to the construction phase increases the cost from $22,100 to $25,800, according to information included in the village board packet.
Even with Dunn Street added into the scope of services, the village board has an option to decide which street projects to complete when the bids come in, said Lynn Niggemann, village administrator-clerk-treasurer.
Adding Dunn Street to the scope of services is a minimal cost, said Scott Gunnufson, village president.
Construction estimates for the street projects are $253,000 for Riverview Avenue from High Street to Viking Drive; $96,000 for High Street from Riverview Avenue to Oak Street; $79,000 for Dunn Street.
If all goes according to plan, construction on the street projects would start in June. Soliciting for bids would take place in February, and the bid opening would be March 18 with the bid being awarded at the March 22 village board meeting.
The Colfax Village Board voted unanimously to include Dunn Street in the scope of services.
Discrepancies
In another matter involving High Street, Shambeau reported that the street is not centered on the right-of-way.
From Riverview to Oak Street, High Street is centered in the middle of the right-of-way, but the street gradually shifts to the south side of the right-of-way farther east, he said.
According to a map included in the village board packet, about halfway between Ash Street and Birch Street, the street is on the southern edge of the right-of-way.
“It gets worse the farther east you go,” Shambeau said.
The road should be an equal distance from the north and south property lines, he noted.
The question is — should the street be left as it is or should the street be moved so it is in the middle of the right-of-way?
As it is now, properties on the south side of the street have less lawn, and properties on the north side of the street have more lawn, Niggemann said.
If the street is moved, properties on the south side will gain lawn, but properties on the north side will lose some of their lawn, she said.
Gary Stene, village trustee, was of the opinion the street should be left “as is.”
Years ago, the north side of High Street was all farm field. Gene Ziebell’s house was the only house there, and from Riverview to Oak Street was just an empty lot, he said.
Twelve feet is quite a bit of property, commented Mark Halpin, village trustee.
What is Rand Bates’ opinion? Halpin asked.
Bates, the director of public works, said he’d had a discussion with Shambeau about the situation and that if it were up to him, he would leave it as is, although leaving it as is “is not the right way.”
There is no engineering reason it cannot work the way it is, Shambeau said.
Moving the street would remove trees and yards, Bates said.
A title search would have to be completed for all of the houses along High Street, and the surveyor’s irons would have to re-set, Shambeau said.
To complete the permanent improvements within the right-of-way, temporary construction easements may be needed for the utilities, he said.
Using “modern requirements” in an older part of the village does not always work, Stene said, noting that trees were lost along Park Drive a few years back in a similar situation where the houses had probably been built in the 1920s and 1930s.
The Colfax Village Board unanimously approved a motion to leave High Street and the right-of-way “as is.”
Other business
In other business, the Colfax Village Board:
• Approved bartender operator’s licenses from January 25, 2021, to June 30, 2021, for Julie Eiseth (Kyle’s Market); Pierce Harvey (Synergy Cooperative); and Morgan Jensen (Synergy Cooperative).
• Learned that an “online audit” of the village’s finances will take place from February 22 to February 24 and that the auditors will want to meet with a village board member.