$1.6 million Colfax river bank stabilization project on track for construction next summer
PROTECTED CONTENT
If you’re a current subscriber, log in below. If you would like to subscribe, please click the subscribe tab above.
Username and Password Help
Please enter your email and we will send you a password reset link.
By LeAnn R. Ralph
COLFAX — The project to keep the Red Cedar River from washing out the wastewater treatment lagoons, for which Colfax has received a $592,000 Community Development Block Grant, is expected to be completed next summer.
The Citizen Participation Plan Committee of the Village of Colfax held a public hearing August 10 to provide information about the river bank stabilization project and to receive public input.
The U.S. Army Corps of Engineers is planning on construction in late spring of 2021 or during the summer, said Jon Strand of CBS Squared.
The process of rip-rapping and restoration of the river bank will not be a long project, and the work is expected to be finished by October, along with the paperwork, he said.
The entire cost of stabilizing the river bank, according to information from the Army Corps of Engineers, would be about $1.6 million, and while federal funds available through the Army Corps would cover 65 percent of the cost, the village of Colfax is responsible for 35 percent, or about $600,000.
The U.S. Department of Housing and Urban Development recently recalculated the income eligibility of Colfax residents. People in the village are now considered to be low to moderate income, which qualified the village to apply for CDBG funds.
Colfax could have applied for up to $1 million but then would have to provide $500,000 in matching funds.
The money from the Army Corps of Engineers is considered to be matching funds, so with the award of the $592,000 as CDBG funds, the only cost to the village was expected to be $35,000 to $40,000 to CBS Squared for the grant application, grant administration and project oversight.
The contract for construction is expected to be awarded by the end of this year, said Lynn Niggemann, village administrator-clerk-treasurer.
All of the village’s portion of the project is paid and amounted to $38,000. The CDBG funds are being held in trust by the Army Corps, she said.
The Army Corps of Engineers will award the contract, Strand said.
As the person conducting project oversight, Strand said he will have to sign off on various aspects of the project, such as the amount of rip-rap that was installed.
The project also requires some quarterly paperwork, he noted.
The Army Corps is not flexible about the schedule. The environmental review is finished, and contractor selection will take place 45 days after the notice is issued. The Army Corps has an organized selection process for the contractor, Strand said.
In other words, “they tell us who will do the work and when it will start,” said Village Trustee Gary Stene.
“Yes,” Strand replied.
Will the village board be receiving monthly updates after the construction starts? Stene asked.
Strand said he was anticipating a monthly progress report that would involve the Army Corps, Niggemann, Rand Bates, director of public works, and Strand as a representative of CBS Squared.
Over the last several decades, the Red Cedar River has steadily eroded the river bank and has come much closer to the lagoons. Estimates are that perhaps one hundred to two hundred feet of river bank have disappeared.
Although the Army Corp of Engineers came to Colfax to view the erosion problem in December of 2014 and wrote the report in 2016, the village noticed a problem with the river bank eroding away near the lagoons long before that.
In August of 2010, a thunderstorm that dumped up to eight inches of rain around the area in a couple of hours caused the bank to erode even more from stormwater run-off.
The wastewater treatment lagoons were built in 1982.