Colfax settles $22,000 in damages for Fourth Ave. delay
By LeAnn R. Ralph
COLFAX — When it’s all said and done, it’s a break-even situation.
The Colfax Village Board at the October 26 meeting approved additional engineering fees for Ayres Associates of $21,945 associated with delays in the Fourth Avenue project and approved assessing liquidated damages of $21,945 against the contractor, RM Schlosser Excavating.
“The contract for Fourth Avenue went way overtime … (Schlosser’s) level of effort fell way short of an average contractor,” said Lisa Fleming, a civil engineer with Ayres Associates.
The liquidated damages included in the contract with Schlosser amounted to $770 per day for every day that the project went over the original 70 days included in the contract to finish Fourth Avenue.
Construction on the project began last spring and ended during the summer.
The Fourth Avenue project was originally scheduled for the fall of 2014, but the contractor ran out of time before cold weather set in.
Colfax still owed $145,678 to Schlosser and subtracted the amount of $21,945 for a final payment to the contractor of $123,733.
The $21,945 was calculated at $770 per day for 28.5 days.
Schlosser was awarded the low bid of $336,767 for the Fourth Avenue project.
The high bid for Fourth Avenue came from Pember Companies out of Menomonie at $424,339.
A1 Excavating, Bloomer, bid $349,311 for the project; Haas Sons out of Thorp bid $353,848; and McCabe Construction, Eau Claire, bid $389,323.
Other street contractors, such as McCabe, A-1 Excavating and Haas, “would have blown through the job in no time,” Fleming said.
Liquidated damages are not intended to be punitive, but instead, are intended to cover a municipality’s extra cost that results through no fault of the municipality, she said.
No Fridays
One of the problems is that the Schlosser crew never worked on Fridays, Fleming said, noting that another part of the problem was that the Schlosser crew did not work as efficiently as they could have.
For example, on one particular Thursday, the crew could have worked two more hours to finish the storm sewer, and if the contractor had worked on Friday, could have started grading the street the next day. Instead, the crew quit at the regular time on Thursday, they did not work on Friday, and in fact, did not get back to grading the street until the following Tuesday, Fleming said.
Not putting in the two extra hours accounted for four days of overrun on the contract, she said.
In another instance, after the curb and gutter had been poured, a grader was used to pack down the base course, and the grader kept bumping the curb, resulting in numerous damaged areas, Fleming said.
Ayres Associates engineers then had to come back to Colfax for additional time to measure and mark the damaged areas that needed to be replaced and then stayed to make sure that all of the broken spots were taken out, she said.
Usually engineers do not visit the job site every day once the underground items are installed, such as sewer and water lines, but in this case, “when they graded, we stayed on site,” Fleming said.
According to a report calculating the extra time Ayres devoted to the project, “There were many days they did not work, but we were checking in daily numerous times with them on status through phone or e-mail, and many days we were on call in case they decided to work. They did not call us. We had to track them down and hope they answered cell phones. There were several days, too, where they did not notify us in time that they were not working, and we went to the job anyway, resulting in lost time.”
37 days
All together, Schlosser went over the amount of time set in the contract by 37 days, but assessing 28.5 days will cover the extra engineering costs, Fleming said.
There is a perception that Ayres controls the work done by contractors, but Ayres is there to work with the contractor and to make sure the work is done, she said.
“I can’t direct them to work Fridays. I can’t direct them to stay two extra hours. I can’t direct them to get another crew in there to work. That’s all their means and methods,” Fleming said.
Scott Gunnufson, village president, said he knew that the over-run on the Fourth Avenue project was frustrating for village residents who live on the street.
“We have an opportunity to finish (out) the project with no additional cost to the village,” he said.
Ayres Associates and Fleming “did an outstanding job” and also operated in good faith after it became known the project would extend far beyond the 70 days, Gunnufson said.
Prior to the village board meeting, the streets committee met and recommended that the village board approve the justification for additional engineering services, the final pay estimate for Schlosser and an amendment to the engineering services contract with Ayres Associates.
The Colfax Village Board unanimously accepted the report detailing the additional hours for Ayres Associates, unanimously approved the final payment for Schlosser of $123,733, and unanimously approved the amendment to the contract for an additional $21,945.
Village Trustee Jeremy Klukas was absent from the meeting.
Village Trustee Keith Burcham attended his first meeting after being appointed to fill the trustee position created by the resignation of Susan Olson.
Other business
In other business, the Colfax Village Board:
• Approved the application for a bartender operator’s license for Barbara Creaser from October 26 to June 30, 2016, for A Little Slice of Italy.
• Approved the application for a bartender operator’s license for Victoria Larson from October 26 to June 30, 2016, for Express Mart.
• Approved a multiple dogs (kennel) license for JoAnn Mayfield for the last three months of 2015. The fee for a license for more than three dogs is $36.50 per year.
• Approved proceeding with burial in Tower Park of the time capsule from the Colfax Sesquicentennial in 2014 after all of the wires running through Tower Park have been located.
• Approved a contract with the Dunn County treasurer’s office to collect the first installment of property taxes. The county is required by state statute to collect the second half of the property taxes, noted Lynn Niggemann, administrator-clerk-treasurer, and Colfax has been contracting with the county treasurer for a number of years to collect the first installment. The cost for the county to collect the first installment is $2.25 per parcel.