Colfax approves $9,000 for municipal building water problems, postpones $54,000
By LeAnn R. Ralph
COLFAX — The Colfax Village Board has approved stripping the Colfax Municipal Building basement and removing the old boilers at a total cost of $8,800 but has postponed action on $54,000 in exterior work.
The village board accepted bids at the September 28 meeting from Air MD Restoration & Recommendations in the amount of $7,900 for removing all cellulose material from the basement and from T&R Recycling in the amount of $900 for removing the two old boilers.
Regarding the bid of $54,371 from A Breeze Construction, Lynn Niggemann, village administrator-clerk-treasurer, said the village would have to check with the state Department of Natural Resources to find out if a stormwater permit is needed.
If a stormwater permit is required, the village will have to hire an engineer to map the drains and easements, she said.
The village also will have to obtain a legal agreement with Bill Berres (Berres Family and Sports Chiropractic) for an easement for drainage on the north side of the building, Niggemann said.
Bob Sworski of CBS Squared quoted a price of $3,000 to $5,000 if engineering services are needed for a DNR permit, she said.
For $54,371, A Breeze Construction is proposing to regrade the green space on the south side of the building to improve drainage, install area drains to capture water coming off the municipal building roof, regrade and pave the parking area in back of the building, install catch basins in the parking lot, run pipe from the roof drain downspouts to the catch basins, and install pipe to drain the catch basins toward the river, remove the window wells on the north and regrade to improve drainage as well as pour concrete to help with draining away water.
Water infiltration problems started in the municipal building basement in 1998, and the basement has not been used since then.
Several torrential rain events this summer have left standing water on the basement floor.
Delays
Scott Gunnufson, village president, questioned whether it would be wise to approve the A Breeze contract contingent upon whether a DNR permit is needed.
A Breeze will not pour concrete after October 15, although if the weather is good, the company could extend the deadline for laying down asphalt until November 15, Niggemann said.
Representatives for A Breeze have said they will do their best to get the exterior work done this year, she said.
Rand Bates, director of public works, said the village installed a catch basin near Iverson Park along Eighteen Mile Creek and did not need a DNR stormwater permit for the project.
Bates said he was told that a permit is not needed as long as the drainage components being installed do not interfere with the water in a stream or a river.
An abstract and a legal description will be needed for the easement, Niggemann said.
Mark Halpin, village trustee and chair of the public property committee, suggested that since time is of the essence for completing the work this fall, perhaps the village board could hold a special meeting when information is available about the DNR permit and the easement.
If a DNR permit is required, it takes about 30 days to get the permit, Niggemann said.
The village board needs more information on the time frame and cost for an easement, and if a DNR permit is required, board members must know the costs associated with the permit, Gunnufson said.
The title work for the abstract for the easement will perhaps take the longest, Niggemann said.
“We need to get the fine print out of the way,” Gunnufson said.
Other work
If the village board cannot move forward with the exterior work, what else can be done in the meantime, Halpin wondered.
“Is there something we can do?” he asked.
One task would be to “get rid of everything in the basement,” Bates said.
“We have to get everything out of the basement no matter what,” he said.
The village board could take action on the Air MD and T&R Recycling bids and bring the third bid back for the outside work when the additional information is obtained, Gunnufson said.
Dave Wolff, village trustee, attended the public property committee meeting the week before that was devoted to the bids for the municipal building.
Sworski told the public property committee that the municipal building basement and the building itself is structurally sound, Wolff noted.
The Colfax Village Board voted unanimously to accept the bid for $900 from T&R Recycling to remove the two old boilers and the bid for $7,900 from Air MD Restoration & Recommendations.
The Colfax Village Board also voted unanimously to postpone action on the bid from A Breeze Construction for $54,371 until additional information about the DNR permit and the easement has been obtained.
The village of Colfax has $77,912 in one designated fund for the municipal building basement and $165,280 in another fund designated for village hall improvements.
The $77,912 comes from $50,000 the village board set aside for the municipal building basement after the 1998 report and from private donations for improving the basement.
The Colfax Village Board unanimously approved a resolution to move money from the restricted fund for the municipal building to the general fund to pay for building improvements.